Our team was proud to support a manufacturing client by remediating a contaminated brownfield site while meeting an aggressive construction schedule. Working alongside Haley & Aldrich, we helped design and construct a cap and containment system—including a slurry wall, perimeter toe drain, and asphalt cap—despite unexpected lead contamination and tight weather constraints.

By streamlining operations, maximizing equipment utilization, and consolidating tasks, the project was completed on time and under budget. Our collaborative efforts also enabled a $45,000 savings in permitting costs through the use of a code variance.